The tender is for strengthening a water conductor. Bidders must submit bids online by January 13, 2026, and the opening date is January 14, 2026. The bid validity is 90 days. The original instruments for the tender document cost and bid security declaration must be submitted at the time of allotment. A security deposit of 3% of the bid price is required within 7 days of receiving the Letter of Award (LOA). The work must be completed within the stipulated time, and a penalty of up to 10% of the contract value may be imposed for delays. The contractor must supply key construction materials according to specifications. The contractor must have an average annual turnover of civil works during the last three years to the tune of 40% of the value of the contracts applied. The contractor must have experience in successfully completing or substantially completing at least one civil work of the same nature, at least 33% of the proposed contract value within a year during the last 3 years.
The date of start of the work shall commence from 7 days from the date of opening of the bid. The date of start of the work shall commence from 7 days from the date of opening of the bid.
Work done claim shall be paid as and when funds are made available by the competent authority. Work done claim shall be paid as and when funds are made available by the competent authority the executing agency shall not be held a responsible for delay in payment on account of nonrelease of funds.
The defect liability period is 06 months after the date of completion. defect liability period: 06 months after date of completion.
The award of contract shall be subject to administrative approval and technical sanction. he award of contract shall be subject to accord of administrative approval technical sanction.
Bidders must have an average annual turnover of civil works during the last three years to the tune of 40% of the value of the contracts applied. he bidder must have an average annual turnover of civil works during the last three years to the tune of 40 of the value of the contracts applied.
In case of delay in completion of the work beyond the stipulated time, a penalty of up to 10% of the contract shall be imposed. in case of delay in completion of the work beyond stipulated time of completion, penalty up to 10 of the contract shall be imposed.
The intending tenderers are advised to visit the site to acquaint themselves with the site condition for quoting genuine and workable rates. he intending tenderers are hereby advised to visit the site to acquaint themselves with the site condition for quoting genuine and workable rates.