Open e-tender for overhauling pumps and replacing membranes in RO plant at NCTPS III, Chennai. EMD of Rs. 12,400 required via online payment. Bids due **** at 14:00, opening **** at 14:30. BQR: experience in similar work worth Rs. 4,44,020 in last 10 years, annual turnover above Rs. 4,44,020. Contract period 60 days. Payment: 90% after completion, 10% retention after guarantee period. LD 0. 5% per week, max 10%. Guarantee period 6 months.
Bids must be submitted by **** at 14:00. The work should be completed within 60 days during the annual overhaul period. date of closing of online etender **** **** pm
90% of payment including GST is paid after completion of works and receipt of bills. The balance 10% is retained and paid after the guarantee period. 90 of payment all inclusive prices including gst will be paid after completion of works
The guarantee period for workmanship is 6 months from the date of completion. Any defects noticed must be rectified by the contractor at no cost. the guarantee period for the workmanship is 6 six months from the date of completion of work
The contract is awarded to the lowest eligible tenderer. to accept the lowest eligible tender
Bidders need experience in annual maintenance/overhauling of SWRO/BWRO skids in a thermal power station of 210 MW or above, for a value not less than Rs. 4,44,020 in a single order within the last 10 years. previous experience in carrying out annual maintenanceoverhauling rectification of swrobwro skid in rodm plant
Liquidated damages for delay are 0. 5% of the contract price per week of delay, with a maximum of 10% of the contract value. levy of liquidated damages for delay at half percent 0. 5 of the contract price of the undeliveredcompleted items for each calendar week of delay
Clarifications to tender documents must be requested before 48 hours of opening of tenders. in case any tenderer asks for a clarification to the tender documents before 48 hours of opening of tenders
Bids will be summarily rejected if EMD requirements are not complied with, if BQR is not satisfied, or if bids are received through consortium or joint venture. tenders will be summarily rejected if the emd requirements are not complied with