The contract is for cleaning and removal of garbage ash from boiler and auxiliaries at Panipat Thermal Power Station for a period of 24 months. The estimated cost is Rs. 54,50,208 inclusive of GST @18%. Bidders must meet specific PQR eligibility criteria, including minimum 1 year experience and average annual turnover of not less than Rs. 27,25,104 in the last 3 consecutive financial years. Payment is made on the basis of actual work carried out on a unit rate basis. The contract period is 24 months, extendable by up to three months.
The work shall be started within 7 days of issue of loi work order, whichever is earlier unless otherwise directed by the issuer of tender. The work shall be started within 7 days of issue of loi work order, whichever is earlier
Payment shall be made after deducting 6% security deposits from each bill subject to a maximum of 5% of final contract price value and statutory deductions, of the monthly running bill shall be made after satisfactory completion of work done. 100 payment, after deducting 6 security deposits from each bill subject to a maximum of 5 of final contract pricevalue and statutory deductions, of the monthly running bill shall be made after satisfactory completion of work done.
The work as a whole will be allotted in a single part to the bidder who is overall lowest in the respective bidders or the whole work against this tender shall be awarded to a single firm whose overall quoted equated rates are lowest for the complete package. the work as a whole will be allotted in a single part to the bidder who is overall lowest in the respective bidders or the whole work against this tender shall be awarded to a single firm whose overall quoted equated rates are lowest for the complete package.
Bidders must have minimum 01 year experience of cleaning work in areas of boiler turbine switchyard coal handling plant in any thermal power station of hpgcl ntpc psus private thermal power plant. a bidders must have minimum 01year experience of cleaning work in areas of boilerturbineswitchyardcoal handling plant in any thermal power station of hpgclntpcpsusprivate thermal power plant.
If the contractor submits the monthly bill between the 11th and 20th day of the month, a penalty at the rate of **** of the contract price shall be levied next calendar month. if the contractor submits the monthly submitted by the end of the bill between the 11th and 20th day of the month, a penalty at the rate of **** of the contract price shall next calendar month.
The tenderer is advised to inspect the site of work the environment and make acquaint with actual work and other prevalent conditions, facilities available, position of material and labour. the tenderer is advised to inspect the site of work the environment and make acquaint with actual work and other prevalent conditions, facilities available, position of material and labour.
Bidders who do not have contractor id on hewp cannot participate in tendering process. bidders who does not have contractor id on hewp cannot participate in tendering process.
****
Payment shall be released by the sr. accounts officeraccounts officer, ptps, panipat through rtgsneft, in the account of the contractor which shall be used by the contractor for payment of wages to the workers in their saving account and other statutory obligations like epfesietc. payment shall be released by the sr. accounts officeraccounts officer, ptps, panipat through rtgsneft, in the account of the contractor which shall be used by the contractor for payment of wages to the workers in their saving account and other statutory obligations like epfesietc.