Works contract for APH B maintenance at NCTPS III, Chennai. EMD of Rs. 1,04,500 required via online payment. Bids submitted online via tntenders. gov. in by **** 14:00. Opening on **** 14:30. BQR: experience in regenerative air preheater repair in thermal power stations (210 MW+) worth Rs. 37,33,350 in last 10 years; annual turnover above Rs. 37,33,350 in one of FY **** to **** period 60 days. Payment: 90% after completion, 10% after guarantee period. Guarantee: 18 months material, 6 months workmanship. LD at 0. 5% per week, max 10%. Security deposit 5% of contract value.
The work should be completed within 60 days during the AOH period. As per the document: period of contract: 60 days the work should be completed during aohperiod.
90% of payment is made after completion of works and receipt of bills. The remaining 10% is paid after the guarantee period. The document states: 90 of payment all inclusive prices including gst will be paid after completion of works and after receipt of bills.
Guarantee period for material is 18 months from receipt or 12 months from commissioning, whichever is later, with an overall cap of 24 months. Workmanship guarantee is 6 months. The document states: the guarantee period for the supply portion is 18 eighteen months from the date of receipt of material at site or 12twelve months from the date of commissioningerectionwhichever occur later.
Bidders need experience in regenerative air preheater repair works in thermal power stations (210 MW or above) with a single order value of not less than Rs. 37,33,350 in the last ten years. The document states: the bidder should have previous experience in carrying out regenerative air pre heater repair works in thermal power station having unit capacity of 210 mw or above.
Liquidated damages for delay are 0. 5% of contract price per calendar week, with a maximum of 10% of contract value. The document states: the contractor is liable at the discretion of the competentauthority concerned to the levy of liquidated damages for delay at half percent 0. 5 of thecontract price of the undeliveredcompleted items for each calendar week of delay and totalshall not exceed maximum of 10 of the contract value.
Clarifications to tender documents must be sought before 48 hours of opening of tenders. The document states: in case any tenderer asks for a clarification to the tender documents before 48 hours of openingof tenders, the cenctpsiii or seminctpsiii, tnpgcl, chennai120 will clarify the same.
Tenders will be summarily rejected if EMD requirements are not complied with, if BQR is not satisfied, or if bids are received through consortium or joint venture. The document states: tenders will be summarily rejected if the emd requirements are not complied with and if the bids are received through consortium or joint venture, the same will not be considered and the bids will be rejected.