Overhauling of oil heater assembly at Tuticorin Thermal Power Station Unit III. Period of work: 20 days from site handover. EMD: Rs. 5,800 payable online. Bids due **** at 14:00 hrs; opening **** at 14:00 hrs. BQR: experience in furnace heavy oil heater overhaul in 210 MW or above thermal stations, annual turnover of Rs. 1. 54 lakhs. Payment: 95% within 90 days, 5% after guarantee period. Guarantee: 12 months from commissioning or 18 months from supply. LD: 0. 5% per week, max 10%. No arbitration; CE TTPS decision final.
The work must be completed within 20 days from the date of handing over of site. As stated: period of work: 20 days from the date of handing over of site.
95% of work value paid within 90 days from satisfactory completion, balance 5% after guarantee period. As stated: 95 payment will be paid within 90 days from the date of satisfactory completion of work. balance 5 will be paid within reasonable time thereafter after completion of guarantee period.
The reconditioned equipment is guaranteed for 12 months from commissioning or 18 months from supply, whichever is later, with overall guarantee of 24 months. As stated: guaranteed for a satisfactory performance of 12 months from the date of commissioning or 18 months from the date of supply whichever is later.
Bidders need experience in furnace heavy oil heater overhaul in 210 MW or above thermal stations and annual turnover of at least Rs. 1. 54 lakhs. As stated: previous experience in furnace heavy oil heater overhaul works in any one of the 210 mw as a single unit or above capacity thermal power generating stations.
Liquidated damages of 0. 5% of total contract price per week of delay, maximum 10%. As stated: a sum of half percent 0. 5 of the total contract price for each completed week of delay. the total liquidated damages shall not exceed ten percent 10 of the contract price.
Clarifications must be sought before 48 hours of opening of tenders. As stated: in case any tenderer asks for a clarification to the tender documents before 48 hours of opening of tenders, the chief engineer ttps will clarify the same.
Bids will be summarily rejected if EMD requirements not complied, consortium/JV bids, not satisfying BQR, or no GST registration. As stated: tenders will be summarily rejected if a the emd requirements are not complied with. b if the bids are received through consortium or joint venture.