Replacement of failed stems in HP, IP control valves and ESVs at Mettur Thermal Power Station I. Work period: 20 days. EMD: Rs. 6,900. Bids via www. ***. *. * date for submission: **** at 14:00 hrs. Opening: **** at 09:00 hrs. BQR: executed works in overhauling/maintenance of main turbine and auxiliaries in single order over Rs. 1. 79 lakhs. Payment: 95% within 90 days, 5% withheld. Guarantee: 1 year free repair of defective work. Liquidated damages: 0. 5% per week, max 10%.
The work must be completed within 20 days. As per the tender: the work should be completed within 20 days.
95% payment within 90 days from completion, with interest at SBI 3-month MCLR if delayed. Balance 5% paid with security deposit. 95 payment will be made with time period of 90 days from the date of completion of works.
A guarantee to do defective work free of cost for one year from completion. a guarantee to do the defective work at free of cost for one year from the date of completion of work, against any defective workmanship noticed.
Bidder must have executed works in overhauling/maintenance of main turbine and auxiliaries in a single order over Rs. 1. 79 lakhs. the bidder should have executed works in overhauling maintenance of main turbine its auxiliaries in a single order value of more than rs. 1. 79 lakhs.
Liquidated damages at 0. 5% of contract price per week of delay, max 10%. liquidated damages for the delay in execution, which shall be at half percent 0. 5 of the contract price of the delayed portion, for each completed week of delay.
Bids rejected if BQR documentary proof not uploaded, if consortium/JV bids, or if undertaking not signed. failing which their bid will be summarily rejected and if the bids are received through consortium or joint venture, the same will not be considered and the bids will be rejected.