12/25/2025 - INDIA | OD | SAMBALPUR Medium City
Mahanadi Coalfields Limited- Hq Civil- Welfare N Csr- Civil- Welfare N Csr
Renovation of Two Tennis Courts, Painting, Washing and some development works of Sports Complex area of Jagruti Vihar, MCL HQ ( Retender)
renovation of two tennis courts, painting, washing and some development works of sports complex area of jagruti vihar, mcl hq retender
AI helper
The work must be completed within 90 days from the date of commencement as defined in clause 6. 0 of general terms and condition. The works should be completed as per period specified in the nit from the date of commencement as defined in clause 6. 0 of general terms and condition.
Running account bills shall be paid based on measurement of work recorded by the official authorized by the department for this purpose. Monthly running account bills shall be paid based on measurement of work recorded by the official authorized by the department for this purpose.
The employer will award the contract to the bidder whose bid has been determined to be substantially responsive to the bidding documents and who has offered the lowest evaluated acceptable bid price, provided that such bidder has been determined to be eligible and qualified. Subject to clause no. 20, the employer will award the contract to the bidder whose bid has been determined to be substantially responsive to the bidding documents and who has offered the lowest evaluated acceptable bid price, provided that such bidder has been determined to be: a eligible in accordance with the provisions of clause 2 and b qualified in accordance with the provisions of clause 3.
The bidders shall be required to submit bid with all the information as sought online along with required documents. 3. 1 the bidders shall be required to submit bid with all the information as sought online along with required documents.
In case of failure to complete the work on or before the scheduled date of completion, compensation shall be payable @0. 5 of contract price or revised contract price excluding gst whichever is less per week of delay. in case of failure to complete the work on or before the scheduled date of completion, compensation shall be payable @0. 5 of contract pricerevised contract price excluding gst whichever is less per week of delay.
The bidder, at the bidders own responsibility, cost and risk, is encouraged to visit and examine the site of works and its surroundings, approach road, soil condition, investigation report, existing works, if any, connected to the tendered work, drawings connected to the work, if as available and obtain all information that may be necessary for preparing the bid and entering into a contract for execution of the works. 6. 1 the bidder, at the bidders own responsibility, cost and risk, is encouraged to visit and examine the site of works and its surroundings, approach road, soil condition, investigation report, existing works, if any, connected to the tendered work, drawings connected to the work, if as available and obtain all information that may be necessary for preparing the bid and entering into a contract for execution of the works.
The contractor shall immediately after the award of work draw up a schedule giving dates for submission of samples as required or necessary as per the specification for approval of engineerin charge who shall approve, if found acceptable, promptly so that there is no delay in the progress of the work of the contractor or of the work of any of the subcontractor. 8. 4 the contractor shall immediately after the award of work draw up a schedule giving dates for submission of samples as required or necessary as per the specification for approval of engineerin charge who shall approve, if found acceptable, promptly so that there is no delay in the progress of the work of the contractor or of the work of any of the subcontractor.
The estimated value is 99,89,****. ender value in inr 99, 89, 643
Tender Close Date: