The notice is for the replacement of floor plates of eicher trucks. Bidders must submit an undertaking, and the bid validity is 120 days. The opening date is 20251024. The estimated value is 114979. 00. The work must be completed in 15 days. The bidder must provide a declaration before negotiations. The payment mode is online. The tender is open and item rate. The bidder must provide a certificate with udin from the statutory auditor or cost auditor of the company in case of companies or from a practicing cost accountant or practicing chartered account in respect of suppliers other than companies giving the percentage of local content. The bidder must provide an undertaking regarding relatives as employees of company, disputes resolution clause in case of partnership firmjv, local supplier status of the bidder etc.
The bid notice states “the works should be completed as per period specified in the nit from the date of commencement as defined in clause 6. 0 of general terms and condition. ”
The bid notice states “payment of on account bill shall be made on the engineerincharge s certifying the sum to which the contractor is considered entitled by way of interim payment for the following: a the work executed as covered by the billbills after deducting the amount already paid, thesecurity deposit and such other amounts as may be deductible or recoverable in terms of thework order contract. ”
The bid notice states “any defects which may appear within the defectliability period and arising, in the opinion of the engineerincharge, from lack of conformancewith the drawings and specifications, shall, if so required by the engineerincharge in writing, beremedied by the contractor at his own cost within the time stipulated by the engineerincharge. ”
The bid notice states “the employer will award the contract to the bidder whose bid has been determined to be substantially responsive to the bidding documents and who has offered the lowest evaluated acceptable bid price, provided that such bidder has been determined to be: a. eligible in accordance with the provisions of clause 2 and b. qualified in accordance with the provisions of clause 3. ”
The bid notice states “the bidders shall be required to submit bid with all the information as sought online along with required documents as detailed in etender notice. the qualification eligibility criteria is detailed in etender notice. ”
The bid notice states “if the contractor fails to complete the work and clear the site on or before the date ofcompletion or extended date of completion, he shall without prejudice to any other right orremedy available under the law to the company on account of such breach, pay ascompensation liquidated damages: i @half percent of the contract amountrevised contract amount excluding gstwhichever is less, per week or part of the week of delay. ”
The bid notice states “the bidder, at the bidders own responsibility, cost and risk, is encouraged to visit and examine the site of works and its surroundings, approach road, soil condition, investigation report, existing works, if any, connected to the tendered work, drawings connected to the work, if as available and obtain all information that may be necessary for preparing the bid and entering into a contract for execution of the works. ”
The bid notice states “the contractor shall immediately after the award of work draw up a schedule givingdates for submission of samples as required or necessary as per the specification for approvalof engineerincharge who shall approve, if found acceptable, promptly so that there is no delayin the progress of the work of the contractor or of the work of any of the subcontractor. ”
The bid notice states “all disputes and differences between the parties, as to the construction or operation ofthe contract, or the respective rights and liabilities of the parties on any matter in questionor any other account whatsoever, but excluding the excepted matters detailed belowarising out of or in connection with the contract, within thirty 30 days from aggrievedparty notifying the other party of such matters whether before or after the completiontermination of the contract, that cannot be resolved amicably between the engineerincharge and the contractor within thirty 30 days from one party notifying the other of suchmatters, whether before or after the completion or termination of the contracts, shall bereferred to as a dispute. ”
The bid notice states “the estimated value is ****