The Delhi Jal Board is inviting online percentage rate tenders for desilting trunk sewers in East Zone. The last date for online submission is **** pre-bid meeting will be held on **** must be registered contractors in appropriate categories. The tender requires a two-bid system. Bidders must submit scanned copies of various documents, including registration certificates, EMD details, and affidavits. The work involves desilting of sewers, diversion of flow, and disposal of debris. The contractor must provide safety measures and adhere to labor regulations. The contract includes provisions for performance guarantee, security deposit, and compensation for delays. The work must be completed within 180 days. The contractor must also provide a site office and comply with various safety and environmental guidelines. The tender also includes details on payment terms, insurance, and dispute resolution.
The successful bidder shall have to complete the works within the period mentioned in the nit documents.
The payment of the monthly running bill for the works shall be released in 90 days from the date of recording of pay order.
The defect liability period is 05 years for pipe network works related to both water and sewerage with an expected project cost greater than 3 crore, and for all other works, the defect liability period is 02 year.
The tender is awarded based on the lowest bid price.
The tenders for this contract will be considered only from those bidders proprietorship firms, partnerships firms, companies, corporations, consortia or joint ventures who meet requisite eligibilitycriteria prescribed as under.
In the event the contractor fails to maintain the required progress in terms of clause 10. 4 or to complete the works and clear the site on or before the stipulated date of completion, he shall, without prejudice, to any other right or remedy available under the law to the employer, on account of such breach, pay as agreed compensation the amount calculated at the rates stipulated below or as the engineerincharge whose communication in writing shall be final and binding may communicate on the contract price for every completed daymonth as applicable that the progress remains below that specified in clause 10. 4 or that the works remains incomplete.
The bidder is advised to visit and examine the site of works and its surroundings and obtain for himself, on his own responsibility, all information that may be necessary for preparing the bid and entering into a contract for construction of the works.
The contractor shall, at his own expense and without delay supply to the engineerincharge samples of materials to be used on the works and shall get these approved in advance.
The last date and time for online submission of tender is **** upto 3: 00 p. m.
The tender value is inr 6, 13, 01, 849.