Supply of 15,000 LT pin insulators. EMD Rs. 3,000 via online portal. Bids due **** 14:00 hrs. Opening **** 14:30 hrs. Delivery within 60 days from PO. Payment 100% within 45 days of receipt. Security deposit 5% of PO value. Liquidated damages 0. 5% per week, max 10%. Samples required before bid closing. BQR: min 25 units supplied to state utilities, turnover criteria. Consortium bids rejected.
Delivery is required within 60 days from the date of receipt of purchase order. As per the document: delivery schedule is as follows: . . . 60 days from the date of receipt of po.
Payment is made within 45 days from receipt of materials and bills. The document states: 100% of the all-inclusive price including GST . . . shall be released . . . within a time frame of 45 days from the date of receipt of materials at site and bills.
Bidders must have supplied minimum 25 units of similar materials to state electricity utilities. The document states: the bidders should have manufactured and supplied the minimum quantity of 25 of tendered equivalent materials satisfactorily to state electricity tnpdcls power utilities.
Liquidated damages are 0. 5% per week of delay, capped at 10%. The document states: a sum of half a percent 0. 5 of the all-inclusive price of the undelivered materials for each completed week of delay. The total liquidated damages shall not exceed ten percent 10.
Samples are required before the bid closing. The document states: sample should be submitted . . . on or before the closing the date time of submission of tender . . . offers without sample will be summarily rejected.
Clarifications must be sought before 48 hours of tender opening. The document states: in case, any tenderer asks for a clarification to the tender documents before 48 hours of opening of tenders, the superintending engineer tedc tnpdcl tuticorin will clarify the same.
Bids can be rejected for non-compliance with EMD, BQR, or consortium bids. The document states: tenders will be summarily rejected if . . . the emd requirements are not complied with . . . if the bids are received through consortium or joint venture.