Online tenders are invited for various works by Delhi Jal Board. Bidders must comply with general and special conditions, circulars, and contract conditions issued by the board. The last date for tender download is **** at 11:00 AM, and the last date for online submission is **** at 11:15 AM. The technical bid opening is scheduled for **** at 11:30 AM. Tender fee is non-refundable and must be submitted electronically. Bidders must upload scanned copies of RTGS/NEFT customer confirmations. Eligibility criteria, required documents, and other conditions are detailed in the tender documents available on the Delhi government website. The tender validity is 120 days from the receipt date. The tenderer must be fully conversant with the documents forming part of the contract agreement. Firms registered with Central Purchases Organization and National Small Industries Corporation Limited may be eligible for tender fee exemption (for goods and services reserved for MSME). Additional documents, including affidavits, registration certificates, and performance certificates, are required. Payment to deployed staff is due before the 10th of each month. Tenders of firms that have not completed previous awarded works within the stipulated period will be rejected. Safety measures are mandatory, and contractors are liable for any accidents or damages during work execution. Minimum wage rates prescribed by the Delhi government must be adhered to. The successful bidder will be required to submit original purchase vouchers for verification. If rates quoted are below the justified cost, the bidder must submit a difference as additional performance guarantee. In RMO cases, the timeline of work may be split equally if rates are the same. The tender documents include detailed specifications and terms and conditions.
The bid notice states completion period within 30 days after issue of workorder for item 1, completion period within 60 days for item 2, completion period within 60 days for item 3, completion period within 45 days for item 4, completion period within 60 days for item 5, completion period within 120 days for item 6, completion period within 120 days for item 7, completion period within 60 days for item 8, completion period within 120 days for item 9, completion period within 120 days for item 10, and completion period within 60 days for item 11.
The bid notice states payment shall be made after completion of work on the availability of funds for several items.
The bid notice states guarantee for 12 months for item 5, guarantee for 6 months for item 2, and guarantee for 06 months for item 9.
The bid notice states firms should be registered with labour department, EPF and ESI for deployment works, firm should have valid electrical license for working at all electrical installations, and he firm should have successfully completed similar type of work during last three years with central govt. state govt. costing not less than i one work having 80 cost ii two works having 60 cost. iii three work having 40 cost.
The bid notice states penalty would be imposed **** per hour to the maximum ceiling of **** per day for RMO cases, penalty clause will be applicable if the pumping is affected at any installation due to any reason attributed to the firm, or its worker etc. , willingly or unwillingly, the penalty clause will be applicable. it will be also applicable, if the workers of the firm is are absconding. the firm shall be liable to compensate @0. 5 per day of the total order value for trolley sewage disposal work, and penalty of **** or as deemed fit to competent authority, shall be charged from the total work order value or as the case may be for trolley sewage disposal work.
The bid notice states he bidders are expected to visit the concerned site before quoting submitting bid.