Tenders are invited for inspection and assembly work on travelling water screens at NCTPS II. The process is an open tender two-part system (techno-commercial and price bid). Bidders must have experience in related maintenance/overhaul work and an annual turnover exceeding Rs. 2,72,400 in specified years. The bid closing date is 29. 09. 2026. The L1 tenderer will be decided based on the total contract value. The contract validity period is 180 days from the date of opening of offers.
95% payment will be made within 90 days after satisfactory completion of entire work and submission of bills. 95 payment will be made within 90 days after satisfactory completion of entire work andsubmission ofbills.
The guarantee period for the above work is 6 months from the date of utilization. The guarantee period for the above work is 6 six months from the date of utilization.
The L1 tenderer will be decided for the total contract value. the l1 tenderer will be decided for the total contract value not for the individual item.
The bidder should have experience in rectification of stop log gate seals dewatering and cleaning offore bay chamber in cooling water pump house maintenance overhaul work in travel water screen system maintenance overhaul work in cooling water pump in thermal power station having unit capacity of 210 mwor above for a value of not less than rs. 2, 72, 400 rupees two lakhs seventy two thousand and fourhundred in a single order to tnpgcl tangedcotneb psu osebs govt. organizationgovt. undertakingwithin a period of last ten years between the date of order and the date of tender opening.
If the contractor fails in the due performance of his contract within the time fixed to the contractor or any extension thereof, the contractor is liable at the discretion of the exe. engineer concerned to the levy of liquidated damages for delay at half percent 0. 5 of the contract price of the undelivered incomplete itemsfor each calendar week of delay and total shall not exceed maximum of 10 of the contract value. if the contractor fails in the due performance of his contract within the time fixed to the contractor or any extension thereof, the contractor is liable at the discretion of the exe. engineer concerned to the levy ofliquidated damages for delay at half percent 0. 5 of the contract price of the undelivered incomplete itemsfor each calendar week of delay and total shall not exceed maximum of 10 of the contract value.
Every tenderer is expected to inspect the site before quoting his rates. before quoting his rates.
any clarification in the tender shall be from sought before 48hrs. of due date and time, through email. any clarification in the tender shall be from sought before 48hrs. of due date and time, through email.
Tender will be summarily rejected if received by post courier email and any other mode other than esubmission. tender will be summarily rejected if, 1 received by post courieremail and any other mode other than esubmission.
The bidder should have annual turnover more than rs. 2, 72, 400 rupees two lakhs seventy twothousand and four hundred in any one of the said three financial years ****, **** ****. The bidders annual turnover should be more than rs. 2, 72, 400 rupees two lakhs seventy twothousand and four hundred in any one of the said three financial years ****, **** ****.