Supply of 22kV standalone structure material complete set, 300 sets. EMD of Rs. 1,58,000 required via online mode. Only manufacturers can bid; agents/dealers not considered. Bidders must have supplied similar material in preceding 10 years and have annual turnover above Rs. 40,00,000 in one of last 3 years. Two-part e-tender: technical and price bids. Submission deadline: **** at 02:00 PM. Opening: **** at 3:00 PM. Delivery to central stores, Erode region. Payment 100% after delivery and bill passing. Guarantee 24 months from supply or 18 months from commissioning. Liquidated damages 0. 5% per week, max 10%.
Delivery schedule: inspection call 60 days from receipt of PO, bulk supply 30 days from receipt of despatch instruction. inspection call: 60days from the date of receipt of po. bulk supply: 30 days from the date of receipt of despatch instruction
100% of all-inclusive price released after bill passing. 100 of the allinclusive price including gst of the materials of each consignment shall be released to the vendors
Materials guaranteed for 24 months from supply or 18 months from commissioning. guaranteed for satisfactory operation and good workmanship for a period 24 months from the date of supply or 18 months from the date of commissioning
Only manufacturers with prior supply experience and turnover above Rs. 40,00,000. The tenderers should have supplied the tendered material during any of the preceding ten years and annual turnover of the tenderer shall be more than rs. 40, 00, 000
Liquidated damages 0. 5% per week of delay, max 10%. recover from the supplier as liquidated damages, a sum of half percent 0. 5 of the contract price of the undelivered equipmentsmaterials for each completed week of delay. the total liquidated damages shall not exceed ten percent 10
Not applicable. due date for receipt of sample not applicable
Appeal within 10 days from receipt of order. any tenderer aggrieved by the order of the tender accepting authority competent authority may prefer and appeal to government within ten days from the date of receipt of order
Bids rejected if EMD not complied, BQR not met, or from agents/dealers. tenders received from agents dealers will not be considered and tenders will be summarily rejected if the emd requirements are not complied with