Haryana Board Corporation- Hpgcl- Ptps Panipat
Ch- 12/MP- 7133/Thermal Insulation/2026
AI helper
Completion period for thermal insulation works is 75 days from clearance of front. completion period for thermal insulation works will be 75 days from the clearance of front.
Payment is stage-wise: 50% on 60% work completion, 30% on 100% completion, 10% on joint protocols, and 10% after warranty period. 50 payment of contract value will be paid as stage payment
Warranty period is 180 days from successful commissioning. Defective work must be rectified at contractor's cost. warrantyguarantee defective design, material and workmanship shall be rectified by the contractor at its own cost for a minimum period of 180 days
The contract is awarded to the lowest quoted/equated price for the complete package. the whole work against this tender shall be awarded to a single firm whose overall quotedequated prices are lowest for the complete package.
Bidders must be OEM or registered vendor of HPGCL, or have executed similar thermal insulation works of 110 MW or above in the preceding 7 years. the bidder should be the original equipment manufacturer or a registered vendor of hpgcl as per vendor registration policy for thermal and spray insulation works
Penalty for delay is 1% of total job order value per week or part thereof, subject to maximum of 10%. penalty for delay will be imposed @1 of the total each job order value per week or part thereof subject to maximum of 10
Bids may be rejected if contractor ID on HEWP portal is not available, EMD not deposited, or misleading information is provided. the bidder must have contractor id on hewp portal haryana engineering works portal for participation in the tendering process failing which the firms tender will be straight away rejected.