Procurement of steel sections (sheets, angles, channels, chequered plates) for PSPCL. Three-part bid: EMD, techno-commercial, price bid. EMD Rs 59,380 (2% of tender value, nil if below Rs 5 lakh). Bids due 21 Oct 2026 11:30 hrs, opening 22 Oct 2026 12:00 noon. Reverse auction applies if more than 3 bidders. Payment 95% within 45 days, 5% as performance guarantee. Delivery within 365 days. Penalty 0. 5% per week up to 10%. Warranty 12 months from takeover or 18 months from dispatch. Rates valid 120 days. GST and HSN code required.
Delivery schedule must be indicated in the offer, covering the period for manufacture, testing, inspection and supply. The period of work is 365 days. As per the notice: the offer should clearly indicate monthlybimonthlyquarterly schedule of deliveries.
95% payment within 45 days after dispatch and approval, 5% released after receipt of goods. As stated: 95 payment of contract value prorata for each consignment. . . shall be paid within 45 days.
Supplier must replace defective material free of cost within 12 months from takeover or 18 months from dispatch. As stated: proves defective in material or workmanship within 12 months from the date it is taken over.
Lowest price after reverse auction. As stated: after completion of online reverse auction, the closing price cp shall be considered as l1 rate for further processing.
Firms must submit completion certificates for similar supplies to power companies in last 5 years. New suppliers undergo work appraisal costing Rs 50,000 (outside Punjab) or Rs 25,000 (within Punjab). As stated: firm will submit completion certificate of supplies against purchase orders of tenderedsimilar items.
Penalty of 0. 5% per week of delay, max 10% of undelivered cost. As stated: supplier shall be liable to pay as penalty @1 2 half of one percent of the cost of undelivered supply. . . not exceeding maximum limit of 10.
Tenders rejected if late, incomplete, conditional, without EMD, or from blacklisted firms. As stated: conditional, late or incomplete tenders shall not be accepted and tenders not accompanied by the required amount of earnest money are rejected.