Supply of **** pairs stay clamp for 9 m pole. Open tender, bid closing **** 02:00 pm, opening **** 03:00 pm. Delivery within 45 days to central store Theni. Earnest money deposit Rs. 6,000. Sample required after evaluation. Single delivery location.
Delivery is required within 45 days from the date of receipt of PO. delivery 45 days
Payment for the supplies will be made by e-banking on any one of the nationalised banks, 100% of the all inclusive price within a reasonable time after receipt of materials. payment for the supplies will be made by e-banking . . . 100% of the all inclusive price . . . within a reasonable time after receipt of materials
Guarantee for the satisfactory operation and workmanship for a period 24 months from the date of receipt of materials. guarantee for the satisfactory operation and workmanship for a period 24 months from the date of receipt of materials
Bidders who do not comply with the conditions will not qualify for opening of price bid. bidders who do not comply with the conditions . . . will not qualify for opening of price bid
Liquidated damages, a sum of half a percent 0. 5 of the all inclusive price of the undelivered materials for each completed week of delay. liquidated damages, a sum of half a percent 0. 5 of the all inclusive price of the undelivered materials for each completed week of delay
Sample shall be supplied after evaluation. sample shall be supplied after evaluation
Bid closing **** 02:00 pm. date of closing of online e tender for submission of **** @02: 00 pm
Tenders received without this undertaking will not be opened. tenders received without this undertaking will not be opened