Percentage rate bid for construction of training hall of FIAC Naugaon, Jagatsinghpur. Estimated cost Rs. 25,08,**** excluding GST. EMD Rs. 6,000. Bid document cost Rs. 2,000. Completion period 150 days. Bids via e-procurement portal www. ***. *. * date for online bid submission: **** up to 5:30 PM. Original documents submission: **** to **** bid opening: **** at 2:00 PM. Contractors must be registered with state government or equivalent central government class. GST 18% extra payable. Samples of materials required for testing.
The work is to be completed within 150 days from the date of issue of work order. intended completion period time period assigned 30 days 60 days 90 days 150 days as mentioned against each work for completion as per clause of the list at page02, from the date of issue of work order
GST @18% extra will be paid with the bill against invoice. G. S. T. @18 extra will be paid with the bill against invoice.
Percentage rate bids are invited. percentage rate bids in single cover system and the contractor has to quote percentage excess or less over the estimated cost
Bidders must be registered contractors of class B, C, D with state government or equivalent with central government. percentage rate bids are invited on online mode in single cover system from , B, C D class contractors registered with the state governments and contractors of equivalent grade class registered with central government
Compensation for delay is 1. 5% per month, maximum 10% of tendered value. compensation @1. 5 per month for delay of work, delay to be computed on per day basis. provided always that the total amount of compensation for delay to be paid under this condition shall not exceed 10 of the tendered value of work.
Samples of all materials must be supplied before procurement for testing. sample of all material the contractor shall supply sample of all materials fully before procurement for the work for testing and acceptance
Bids can be rejected for false statements, poor performance, abandonment, delay, or litigation history. bidders can be disqualified for the following reasons. . . a making a false statement or declaration. b past record of poor performance. c past record of abandoning the work half way recession of contract. d past record of inordinate delay in completion of the work. e past history of litigation.
The estimated cost put to tender is Rs. 25,08,**** excluding GST. 2508****