Annual maintenance of LT 415V AC switchgear bus A modules, breaker and bus coupler at TTPS cooling water pump house II. Work period: 7 days from site handover. EMD: Rs. 200 via online payment gateway. Bids via two-part e-tender on tntenders. gov. in. Closing: **** 14:00 hrs; opening: **** 14:00 hrs. BQR: experience in LT 415V AC switchgear maintenance in 210 MW or above thermal power stations. Bid validity: 90 days. Security deposit: 5% of contract value. Payment: 95% within 90 days, 5% after guarantee period. Guarantee: 12 months from commissioning or 18 months from supply. Liquidated damages: 0. 5% per week, max 10%. No arbitration; Chief Engineer's decision final.
Work period is 7 days from the date of handing over of site. period of work : 07 days from the date of handing over of site
95% of work value paid within 90 days from receipt of material in good condition; balance 5% after guarantee period. 95 of work value will be paid within 90 days from the date of receipt of material at ttps stores in good condition
Guarantee for satisfactory performance of 12 months from commissioning or 18 months from supply, whichever later, overall max 24 months. reconditioned repaired equipments shall be guaranteed for a satisfactory performance of 12 months from the date of commissioning or 18 months from the date of supply
Previous experience in maintenance of LT 415V AC switchgear in 210 MW or above thermal power stations. should have previous experience in maintenance of lt 415 v ac switchgear in any one of the 210 mw as a single unit or above capacity thermal power generating stations
Liquidated damages of 0. 5% of total contract price per completed week of delay, max 10%. a sum of half percent 0. 5 of the total contract price for each completed week of delay
Clarifications to tender documents must be sought before 48 hours of opening of tenders. any tenderer asks for a clarification to the tender documents before 48 hours of opening of tenders
Bids summarily rejected if EMD not complied, consortium/JV bids, not satisfying BQR, no GST registration. tenders will be summarily rejected if a the emd requirements are not complied with